I-135 Gold North Junction Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Project Description

Phase 2A

The first phase of the I-135 Gold Project included replacing the southbound I-135 ramp to southbound I-235, replacing the northbound I-135 loop ramp to southbound I-235 with a new two-lane flyover ramp, and extending the acceleration lane on the westbound K-254 ramp to southbound I-135. Work on Gold Project Phase 2A began in April 2021 and was completed in December 2023.

Phase 2B

Gold Project Phase 2B includes a new direct connection for eastbound K-96 traffic from northbound I-235 and new ramps for westbound K-96 traffic at I-135. The direct connection for eastbound K-96 from northbound I-235 was completed in December 2024. Work on the new ramps for westbound K-96 traffic at I-135 is underway, with completion anticipated in Spring 2028.

Project Details

Project Name I-135 Gold North Junction
Project Number KA-3232-01
Location I-235/I-135/K-254 interchange in north Wichita
Scope Interchange improvements
Approximate Length 2.82 miles 
Project Timeline Gold Project Phase 2A began in April 2021 and was completed in December 2023. Phase 2B began in February 2023 and is expected to be completed in Spring 2028.
Construction Cost

Gold Project Phase 2A – $36 million

Gold Project Phase 2B – Approximately $141 million