Home MenuI-135 Gold North Junction Project
Project Description
Phase 2A
The first phase of the I-135 Gold Project included replacing the southbound I-135 ramp to southbound I-235, replacing the northbound I-135 loop ramp to southbound I-235 with a new two-lane flyover ramp, and extending the acceleration lane on the westbound K-254 ramp to southbound I-135. Work on Gold Project Phase 2A began in April 2021 and was completed in December 2023.
Phase 2B
Gold Project Phase 2B includes a new direct connection for eastbound K-96 traffic from northbound I-235 and new ramps for westbound K-96 traffic at I-135. The direct connection for eastbound K-96 from northbound I-235 was completed in December 2024. Work on the new ramps for westbound K-96 traffic at I-135 is underway, with completion anticipated in Spring 2028.
Project Details
| Project Name | I-135 Gold North Junction |
| Project Number | KA-3232-01 |
| Location | I-235/I-135/K-254 interchange in north Wichita |
| Scope | Interchange improvements |
| Approximate Length | 2.82 miles |
| Project Timeline | Gold Project Phase 2A began in April 2021 and was completed in December 2023. Phase 2B began in February 2023 and is expected to be completed in Spring 2028. |
| Construction Cost |
Gold Project Phase 2A – $36 million Gold Project Phase 2B – Approximately $141 million |
Project Materials
FAQs
-
When is the southbound I-135 ramp from 29th Street expected to reopen?