Project Description

As the only Missouri River crossing within a 38-mile area, Centennial Bridge is a vital resource for those who work and live in Leavenworth County, Kansas, and Platte County, Missouri. 

On average, more than 14,300 vehicles use the crossing every day. Unfortunately, the existing bridge is outdated and limited in its ability to transport people and goods. 

In 2011, KDOT began a multi-phase study to determine the future of the existing bridge. After conducting traffic, engineering, environmental, community engagement, and feasibility studies, KDOT determined the structure had exceeded its useful lifespan and that a new bridge was needed. 

Project Benefits:

  • The new bridge will not be tolled.
  • Improving flood resilience in the area.
  • Providing combined use pedestrian and bicycle accommodations.
  • Doubling the number of traffic lanes.
  • Resolving Missouri River navigation challenges.

Project Details

Project Name Route 92 Centennial Bridge 
Project Number KA-6016-01 
Location Leavenworth
Scope The new, four-lane Centennial Bridge will be constructed just to the north of the existing Missouri River crossing. 
Project Timeline Anticipated to let in 2028, conditions permitting
Construction Cost $157 million

 

Anticipated Schedule

2021

December: Project Kick-off

2022

January: Surveying

April: Project Branding, Preliminary Engineering and Design Activities Begin

May: Environmental (NEPA) Studies Begin

May - December: Key Stakeholder Meetings

2023

February: Public Meeting

August: Environmental (NEPA) Public Hearing

October: Field Review

2024

January: Begin Right-of-way (ROW) Activities

2025

Continue Right-of-way (ROW) Activities

2026

Continue Right-of-Way (ROW) Activities and Final Design

 

2027

Summer: Design Complete

Fall: Bid Letting 

2028 

Construction Begins
 

2029

Continue Construction

2030 

Anticipated Construction Completion Date

 

Public Meetings

Events

More Events

Project Materials

Documents

Frequently Asked Questions

Project Group Contacts

Reach out to the Centennial Bridge team:

Email

StaffPhone
Centennial Bridge Project Team(913) 766-2198
Reach out to individual project representatives below: 
StaffPhoneEmail
Tholen, Delaney(785) 817-9365